RERA Effect Clear All Your Doubts

01, Jun, 2017


The new Real Estate Regulatory Act came into effect a month ago, but still developers and builders are struggling to clear various doubts about this new act in effect. Propfrill worked to gather all information about RERA under one topic. Here are the most common question asked regarding the RERA Act :

Q: Who is the ‘promoter’ as per the Real Estate Law?

A: The Act covers all private and public bodies that develop real estate projects for sale. Therefore, the development authorities and housing boards are also in its fold. It also mentions, “where the person who constructs or converts a building into apartments or develops a plot for sale and the person who sells apartments or plots are different persons, both shall be deemed to be the promoters and shall be jointly liable as such for the functions and responsibilities specified, under this Act or the rules and regulations made the render”. Therefore, it stands true in cases where a joint development is in question.

Q: If the ‘promoter’ or ‘allottee’ defaults, what is the rate of payment payable?

A: Rate of interest payable by either the promoter or ALLOTTEE is the same. It has to be specified by the appropriate government in the rules.

Q: What if the Regulatory Authority does not respond?

A: Section 5 of the Act provides that the Authority has to decide on the application within 30 days of its receipt. It further provides that in case the Authority fails to take a decision within the said period of 30 days, the project shall be deemed to be registered.

Q: What is the ‘escrow account’ and ‘separate account’?

A: Section 4(2)(l)(D) provides that the promoter shall maintain a ‘separate account’ for every project undertaken by him wherein seventy percent of the money received from the allottees shall be deposited for the purposes of land purchase and construction. The account has to be self-maintained and is not an escrow account requiring the approval of the Authority for withdrawal. Section 4(2)(l)(D) clearly provides that the funds can only be used for construction and land cost.

Q: When can the promoter withdraw the money from the separate account?

A: The promoter is required to withdraw the amounts from the separate account, to cover the cost of the project, in proportion to the percentage of completion of the project. In addition, the promoter is permitted to withdraw from the separate account after it is certified by an engineer, an architect and a chartered accountant in practice that the withdrawal is in proportion to the percentage of completion of the project.

Q: Who else is under the purview?

A: Section 2(zm) defines the term ‘real estate agents’, which is a very broad and inclusive definition and covers all from of agencies involved in sale and purchase of projects, registered under the Act. Consequently, web-portals etc. engaged in selling plots or apartments are also covered under the Act and are required to comply with the duties and responsibilities as provided therein including under the Rules and regulations made the render.

Q: What is the obligation of the promoter as regards insurance of real estate project?

A: The promoter is required to seek an insurance of the real estate project towards title of the land and towards construction of the project. This provision shall only come into effect after and in the manner as may be notified by the appropriate government.

Q: Are the civil courts and consumer forums barred from entertaining disputes under the Act?

A: As per section 79 of the Act civil courts are barred from entertaining disputes (suits or proceedings) in respect of matters which the Authority or the adjudicating officer or the Appellate Tribunal is empowered under the Act to determine. However, the consumer forums (National, State or District) have not been barred from the ambit of the Act. Section 71 proviso permits the complainant to withdraw his complaint as regards matters under sections 12, 14, 18 and 19, from the consumer forum and file it with the adjudicating officer appointed under the Act.

Q: What is the punishment prescribed for non-compliance of the orders of the Appellate Tribunal by the promoter?

A: As per section 64 if the promoter fails to comply with the orders of the Appellate Tribunal, he shall be liable to a penalty for every day of default, which may cumulative extend up to

ten percent of the estimated cost of the real estate project or with imprisonment for a term which may extend up to three years or with both.

Q: What is the punishment prescribed for non-compliance of the orders of the Appellate Tribunal by the allottee?

A: As per section 68, if the allottee fails to comply with the orders of the Appellate Tribunal, he shall be liable to a penalty for every day of default, which may cumulative extend up to ten percent of the cost of the plot/apartment or with imprisonment for a term which may extend up to one year or with both.

Source: Ministry of Housing & Urban Poverty Alleviation, Government of India


Posted by : Satish Singh

Propfrill.com ( GTF Technologies ) shall neither be responsible nor liable for any inaccuracy in the information provided here and therefore the customers are requested to validate the information from the respective developers before making their decision for purchase of properties. The information provided herein have been collected from publicly available sources, and is yet to be verified as per RERA guidelines.*

Click here to go through our terms of use as per RERA guidelines.
Unit of GTF Technologies
Disclaimer: Propfrill.com is a platform which acts a medium for allowing people having converging interests involving real estate transactions, namely the buyer/tenant and owner/broker.Propfrill.com is merely a preliminary medium of contact and exchange of information, users are strongly advised to have independent third party verifications (whether marked verified or not) prior to proceeding with any transactions involving real estate. The onus of finding a genuine property, be it for purchase or rental purpose, lies on the user. This website is meant only for information purposes. It should not be considered/ claimed as an official site...    Read More...